| Owner: | BIM Renewable Energy Joint Stock Company (BIM Group) |
| Capacity: | 325 MWp |
| Service provision period: | Operation in April 2023 - NOW |
| Scope of work: | O&M services for the Power Plant and 220kV Substation; Grass cutting and PV cleaning |
BIM2 solar power plant is located in Phuoc Minh Commune, Thuan Nam District, Ninh Thuan Province with a designed capacity of 325 MWp, of which Phase 1 was put into commercial operation in May 2019 and Phase 2 was put into operation. into commercial operation in December 2020, the expected annual electricity production into the national grid system is 583.792.37 million kWh/year. The O&M POM team took over the operation and maintenance from April 2023, ensuring continuous and stable operation of the plant, complying with the process and state regulations. POM guarantees a Factory Availability Factor (AF) over 99%.